# The A1 Birtley to Coal House Development Consent Order 2021, Paragraph 25

Extent: E+W+S

Network Rail must at all reasonable times afford reasonable facilities to the undertaker and the undertaker's agents for access to any works carried out by Network Rail under this Part of this Schedule during their construction and must supply the undertaker with such information as the undertaker may reasonably require with regard to such works or the method of constructing them.

---
Source: https://www.legislation.gov.uk/uksi/2021/74/schedule/11/paragraph/25 (the official version)
Page: https://openlegislation.uk/a1-birtley-to-coal-house-development-consent-order-2021/schedule-11/paragraph-25
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.