# The A1 Birtley to Coal House Development Consent Order 2021, Paragraph 17: Details of construction compound

Extent: E+W+S

(1) Subject to sub-paragraph (3), in the event that the undertaker proposes to undertake Work No. 5a as provided in paragraph (iii) or (iv) of Work No. 5a comprising a six span or seven span viaduct respectively then the undertaker may only exercise powers of temporary possession over plot 3/13a of the land plans where a plan based upon those in Appendix A to the CEMP showing the extent and layout of the construction compound to be established at Junction 67 within the land delineated by a broken blue line on the Northern Gas Networks Land Ownership Plan has been submitted to and approved in writing by the Secretary of State, following consultation with the relevant planning authority.
(2) In considering the details to be submitted in terms of sub-paragraph (1), the undertaker and the Secretary of State shall have regard to—
(a) the construction requirements of the chosen engineering design for Work No. 5a; and
(b) the need to minimise the temporary possession of land within plot 3/13a of the land plans so far as reasonably practical.
(3) In the event that the undertaker proposes to undertake Work No. 5a as provided in paragraph (iii) or (iv) of Work No.5a then the undertaker shall be restricted to exercising the power of temporary possession over plot 3/13a to that part of the land identified in the details approved in terms of sub-paragraph (1).

---
Source: https://www.legislation.gov.uk/uksi/2021/74/schedule/2/paragraph/17 (the official version)