# The A12 Chelmsford to A120 Widening Development Consent Order 2024, Paragraph 18: Junction 21

Extent: E+W

(1) Requirement 10 (detailed design) is to be read subject to the provisions of this requirement.
(2) The detailed design for the proposed A12 junction 21 (“junction 21”) must contain the revised design detail specified in sub-paragraph (3) of this requirement and submitted to and approved by the relevant local highway authority.
(3) Subject to sub-paragraph (5) the detailed design for junction 21 must include a two-lane exit from both the junction 21 northern roundabout to the A12 northbound slip road and from the junction 21 southern roundabout to the A12 southern slip road.
(4) Junction 21 must be constructed in accordance with the approved details.
(5) No application for approval of the scheme under sub-paragraph (2) may be made in respect of proposals which would give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement.

---
Source: https://www.legislation.gov.uk/uksi/2024/60/schedule/2/paragraph/18 (the official version)
Page: https://openlegislation.uk/a12-chelmsford-to-a120-widening-development-consent-order-2024/schedule-2/paragraph-18/enacted
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.