# The A12 Chelmsford to A120 Widening Development Consent Order 2024, Paragraph 23: Further information

Extent: E+W

(1) In relation to any part of an application made under this Schedule, the approving authority has the right to request such further information from the undertaker as is necessary to enable the approving authority to consider the application.
(2) In the event that the approving authority considers such further information to be necessary, the approving authority must, within 21 business days of receipt of the application, notify the undertaker in writing specifying the further information required and (if applicable) to which part of the application it relates. In the event that the approving authority does not give such notification within that 21 business day period the approving authority is deemed to have sufficient information to consider the application and is not subsequently entitled to request further information without the prior agreement of the undertaker.
(3) Where further information is requested under this paragraph in relation to part only of an application, that part is treated as separate from the remainder of the application for the purposes of calculating the time periods referred to in paragraph 22 (applications made under requirements) and in this paragraph.
(4) In this paragraph, “business day” means a day other than Saturday or Sunday which is not Christmas Day, Good Friday or a bank holiday under section 1 (bank holidays) of the Banking and Financial Dealings Act 1971.

---
Source: https://www.legislation.gov.uk/uksi/2024/60/schedule/2/paragraph/23 (the official version)
Page: https://openlegislation.uk/a12-chelmsford-to-a120-widening-development-consent-order-2024/schedule-2/paragraph-23
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.