(1) No part of the authorised development is to commence until the Second Iteration EMP for that part has been submitted to and approved in writing by the Secretary of State, following consultation with the relevant planning authority and the Environment Agency on matters related to its functions.
(2) The authorised development must be constructed in accordance with the Second Iteration EMP.

---