# The A122 (Lower Thames Crossing) Development Consent Order 2025, Paragraph 23: Notice of determination

Extent: E+W

(1) Subject to sub-paragraph (2) or (3), the MMO must give notice to the undertaker of the determination of the return within 30 business days of the day immediately following that on which the return is received by the MMO, or as soon as reasonably practicable after that date.
(2) Where the MMO has made a request under paragraph 21, the MMO must give notice to the undertaker of the determination of the return no later than 30 business days of the day immediately following that on which the further information is received by the MMO, or as soon as reasonably practicable after that date.
(3) Where the MMO determines it is not reasonably practicable to make a determination pursuant to sub-paragraph (1) or (2) within 30 business days, it must notify the undertaker as soon as reasonably practicable and provide confirmation in writing of the intended determination date.
(4) Where the MMO refuses the return the refusal notice must state the reasons for the refusal.

---
Source: https://www.legislation.gov.uk/uksi/2025/462/schedule/15/paragraph/23 (the official version)
Page: https://openlegislation.uk/a122-lower-thames-crossing-development-consent-order-2025/schedule-15/paragraph-23
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.