# The A14 Cambridge to Huntingdon Improvement Scheme Development Consent Order 2016, Paragraph 17: Traffic Monitoring and Mitigation

Extent: E+W

(1) No part of the authorised development is to commence until written details of a traffic impact monitoring and mitigation scheme has been submitted to and approved in writing by the highway authority.
(2) The traffic impact monitoring and mitigation scheme must include—
(i) a before and after survey to assess the changes in traffic;
(ii) the locations to be monitored and the methodology to be used to collect the required data;
(iii) the periods over which traffic is to be monitored;
(iv) the method of assessment of traffic data;
(v) control sites to monitor background growth;
(vi) the implementation of monitoring no less than 3 months before the implementation of traffic management on the existing A14;
(vii) agreement of baseline traffic levels;
(viii) the submission of survey data and interpretative report to the highway authority; and
(ix) a mechanism for the future agreement of mitigation measures.
(3) The scheme approved under sub-paragraph (1) must be implemented by the undertaker.

---
Source: https://www.legislation.gov.uk/uksi/2016/547/schedule/2/paragraph/17 (the official version)
Page: https://openlegislation.uk/a14-cambridge-to-huntingdon-improvement-scheme-development-consent-order-2016/schedule-2/paragraph-17
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.