# The A14 Cambridge to Huntingdon Improvement Scheme Development Consent Order 2016, Paragraph 8: Archaeology

Extent: E+W

(1) No authorised development is to commence until a written scheme for the investigation of areas of archaeological interest, reflecting the mitigation measures included in the environmental statement, has been submitted to and approved in writing by the Secretary of State.
(2) Prior to the submission of the written scheme to the Secretary of State for approval under paragraph 8(1), the relevant planning authority must be consulted on its content.
(3) The authorised development must be carried out in accordance with the scheme as approved under sub-paragraph (1).

---
Source: https://www.legislation.gov.uk/uksi/2016/547/schedule/2/paragraph/8 (the official version)