# The A14 Cambridge to Huntingdon Improvement Scheme Development Consent Order 2016, Paragraph 3: Girton Interchange A14 Eastbound Link

Extent: E+W

A 2.1 kilometre length of new highway to be classified as part of the A14 Trunk Road commencing from a point 65 metres north-west of the point where Beck Brook passes below the existing A14 Trunk Road in a culvert (to the west of the existing Girton Interchange) and continuing in a south-easterly direction for a distance of 2048 metres to its junction with the existing A14 Trunk Road,
identified by a blue line on the classification of roads plans – sheet 2.

---
Source: https://www.legislation.gov.uk/uksi/2016/547/schedule/3/paragraph/3 (the official version)
Page: https://openlegislation.uk/a14-cambridge-to-huntingdon-improvement-scheme-development-consent-order-2016/schedule-3/paragraph-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.