The A160/A180 (Port of Immingham Improvement) Development Consent Order 2015 (“the original Order”)f1, which granted development consent within the meaning of the Planning Act 2008 (“the Act”), contains correctable errors as defined in paragraph 1(3) of Schedule 4 to the Actf2.

Before the end of the relevant period, as defined in paragraph 1(6)(a) of Schedule 4 to the Act, the Secretary of State received a written request for the correction of errors in the original Order.

In accordance with paragraph 1(7) of Schedule 4 to the Act, the Secretary of State has informed North East Lincolnshire Council and North Lincolnshire Council, the local planning authorities for the area in which the land to which the original Order relates is situated, that the request has been received.

The Secretary of State, in exercise of the powers conferred by section 119 of, and Schedule 4 to, the Act, makes the following Order—

Annotations

Footnotes

f1

S.I. 2015/129.

f2

2008 c. 29. Paragraph 1 of Schedule 4 was amended by paragraphs 1 and 70 of Schedule 13 and Part 20 of Schedule 25 to the Localism Act 2011 (c. 20). There are other amendments to paragraph 1 of Schedule 4 that are not relevant to this Order.