(1) No authorised development is to commence until written details of the surface and foul water drainage system, reflecting the mitigation measures in chapters 2, 9 and 15 of the environmental statement and including means of pollution control and design details of the pumping stations to be constructed as part of the associated development to manage surface run off, have been prepared, submitted to and approved in writing by the Secretary of State, following consultation with the relevant planning authority and the Environment Agency.
(2) The drainage system must be constructed in accordance with the approved details referred to in paragraph (1).

---
Source: https://www.legislation.gov.uk/uksi/2015/129/schedule/2/paragraph/16 (the official version)
Page: https://openlegislation.uk/a160a180-port-of-immingham-improvement-development-consent-order-2015/schedule-2/paragraph-16
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.