# The A19/A1058 Coast Road (Junction Improvement) Development Consent Order 2016, Schedule 1: AUTHORISED DEVELOPMENT

Extent: E+W+S

A nationally significant infrastructure project as defined in sections 14 and 22 of the 2008 Act, comprising—
Work No. 1a - the construction of one half of a new bridge to carry the westbound A1058 Coast Road over the A19 cutting.
Work No. 1b - the construction of one half of a new bridge to carry the eastbound A1058 Coast Road over the A19 cutting.
Work No. 1c - the construction of a new bridge to carry the southern section of the A19 Roundabout over the A19 cutting.
Work No. 1d - the construction of a new bridge to carry the northern section of the A19 Roundabout over the A19 cutting.
Work No. 1e - the construction of a new southbound A19 on-slip road to the south of the A19/A1058 Coast Road junction.
Work No. 1f - the construction of a new northbound A19 off-slip road to the south of the A19/A1058 Coast Road junction predominantly through utilisation of the existing A19 northbound carriageway.
Work No. 1g - the construction of a new northbound A19 on-slip road to the north of the A19/A1058 Coast Road junction.
Work No. 1h - the construction of a new southbound A19 off-slip road to the north of the A19/A1058 Coast Road junction.
Work No. 1i - the construction of 2 new shared-use bridges over the eastbound A1058 Coast Road off-slip road and on-slip road to connect the existing footways and cycle tracks to the east and west of the junction to the footway and cycle track on the A1058 Coast Road through the A19/A1058 Coast Road junction.
Work No. 1j - the construction of a new section of A19 dual carriageway under the existing A19/A1058 Coast Road junction.
Work No. 1k - the widening of Middle Engine Lane Railway Bridge to the north of the A19/A1058 Coast Road junction.
Work No. 1l - the widening of the Silverlink road on the north-east of the A19/A1058 Coast Road junction to provide an additional southbound lane on the immediate approach to the A19 roundabout.
Work No. 1m – works on the A19 to tie in the proposed works at the southern extent of the authorised development with the existing highway layout.
Work No. 1n – the construction of a revised road cross section on the A19 to include an auxiliary lane in addition to two lanes on the A19 mainline in both north and southbound directions.
Work No. 1o – works on the A19 to tie in the proposed works at the northern extent of the authorised development with the existing highway layout.
Work No. 1p – the construction of a new traffic signal installation incorporating Microprocessor Optimised Vehicle Activation and enhanced non-motorised user facilities at the A19 roundabout.
Work No. 1q – a combined footway and cycle track between the A19/A1058 Coast Road junction and the A19/A193 Wallsend junction adjacent to the A19 northbound carriageway.
Work No. 1r – a combined footway and cycle track adjacent to the A19 southbound on-slip road linking the bus stop on the A1058 Coast Road westbound off-slip road and the access to the Tyne Tunnel Trading Estate.
Work No. 1s – concrete repair works to the existing A1058 structures that support the A1058 Coast Road over the A19 roundabout.
Work No. 2a – the diversion of a Northern Gas Network medium pressure main through the new bridge constructed to carry the southern section of the A19 roundabout over the A19 cutting.
Work No. 2b - the construction of a new potable water main for Northumbrian Water Limited along Middle Engine Lane and Middle Engine Railway bridleway.
Work No. 2d – the diversion of British Telecommunications Public Limited Company cables through the new bridge constructed to carry the northern section of the A19 roundabout over the A19 cutting.
Work No. 2e – the diversion of Northern Powergrid high voltage cables through the new bridge constructed to carry the A1058 Coast Road over the A19 cutting.
Work No. 2f – the diversion of Northern Gas Network intermediate pressure mains within the verges of the A19 southbound on slip road and off slip road.
Work No. 2g – the diversion of a Northern Gas Network medium pressure main within the verge of the A19 southbound on slip road.
Work No. 2h – the diversion of Northern Powergrid low voltage cables within the Silverlink.
In connection with the construction of any of those works, further development within the Order limits consisting of—
(a) alteration to the layout of any street permanently or temporarily, including but not limited to increasing the width of the carriageway of the street by reducing the width of any kerb, footpath, footway, cycle track or verge within the street; altering the level or increasing the width of any such kerb, footway, cycle track or verge; and reducing the width of the carriageway of the street;
(b) works required for the strengthening, improvement, maintenance or reconstruction of any street;
(c) refurbishment works to any existing bridge,
(d) ramps, means of access, non-motorised links, footpaths, cycle tracks and crossing facilities;
(e) embankments, viaducts, aprons, abutments, shafts, foundations, retaining walls, drainage, outfalls, ditches, wing walls, highway lighting, fencing and culverts;
(f) street works, including breaking up or opening up a street, or any sewer, drain or tunnel under it; tunnelling or boring under a street; works to place or maintain apparatus in a street; works to alter the position of apparatus, including mains, sewers, drains and cables;
(g) works to alter the course of or otherwise interfere with a watercourse;
(h) landscaping and other works to mitigate any adverse effects of the construction, maintenance or operation of the authorised development;
(i) works for the benefit or protection of land affected by the authorised development;
(j) works required for the strengthening, improvement, maintenance or reconstruction of any streets;
(k) works to alter or remove road furniture;
(l) site preparation works, site clearance (including fencing, vegetation removal, demolition of existing structures and the creation of alternative footpaths); earthworks (including soil stripping and storage, site levelling);
(m) establishment of site construction compounds, temporary vehicle parking, construction fencing, perimeter enclosure, security fencing, construction related buildings, welfare facilities, construction lighting and haulage roads; and
(n) such other works, working sites, storage areas and works of demolition, as may be necessary or expedient for the purposes of or in connection with the construction of the authorised development.

---
Source: https://www.legislation.gov.uk/uksi/2016/73/schedule/1 (the official version)