# The A19/A184 Testo's Junction Alteration Development Consent Order 2018, Paragraph


Work No. 21 — The construction of a new footway 175 metres in length to serve as a bus stop access, commencing at the bridleway/crossing facilities to the southwest of Testo's roundabout (Work No. 14) and tying into the existing footway 175 metres west of Testo's roundabout, as shown between points 2/18 and 2/35 on Sheet 2 of the Streets, Rights of Way and Access Plans.

---
Source: https://www.legislation.gov.uk/uksi/2018/994/schedule/1/paragraph/wrapper23n1 (the official version)
Page: https://openlegislation.uk/a19a184-testos-junction-alteration-development-consent-order-2018/schedule-1/paragraph-wrapper23n1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.