# The A19/A184 Testo's Junction Alteration Development Consent Order 2018, Paragraph


Work No. 29 — The construction of a new southbound A19 off-slip 720 metres in length, commencing at the new A19 dual carriageway (Work No. 2) and tying into the realigned Testo's roundabout (Work No. 22), as shown between points 3/2 on Sheet 3 and 2/29 on Sheet 2 of the Streets, Rights of Way and Access Plans including embankments, cuttings, roadside furniture, signage, electrical connections and strengthening works.

---
Source: https://www.legislation.gov.uk/uksi/2018/994/schedule/1/paragraph/wrapper31n1 (the official version)
Page: https://openlegislation.uk/a19a184-testos-junction-alteration-development-consent-order-2018/schedule-1/paragraph-wrapper31n1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.