# The A19/A184 Testo's Junction Alteration Development Consent Order 2018, Paragraph 2: Time limits


The authorised development must commence not later than the expiration of 5 years beginning with the date that this Order comes into force.

---
Source: https://www.legislation.gov.uk/uksi/2018/994/schedule/2/paragraph/2 (the official version)
Page: https://openlegislation.uk/a19a184-testos-junction-alteration-development-consent-order-2018/schedule-2/paragraph-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.