# The A282 Trunk Road (Dartford-Thurrock Crossing Charging Scheme) Order 2013, Article 16: Review

Extent: E+W

(1) Before the end of the review period, the Secretary of State must—
(a) carry out a review of this Order,
(b) set out the conclusions of the review in a report, and
(c) publish the report.
(2) The report must in particular—
(a) set out the objectives intended to be achieved by the regulatory system established by this Order,
(b) assess the extent to which those objectives are achieved, and
(c) assess whether those objectives remain appropriate and, if so, the extent to which they could be achieved with a system that imposes less regulation.
(3) “review period” means the period of five years from 1st October 2013.

---
Source: https://www.legislation.gov.uk/uksi/2013/2249/article/16 (the official version)
Page: https://openlegislation.uk/a282-trunk-road-dartford-thurrock-crossing-charging-scheme-order-2013/article-16