# The A30 Chiverton to Carland Cross Development Consent Order 2020, Paragraph 3: Construction Environmental Management Plan


(1) No part of the authorised development is to commence until a CEMP for that part has been prepared in consultation with the relevant planning authority, the local highway authority and (on matters related to its functions) the Defence Infrastructure Organisation and submitted to and approved in writing by the Secretary of State.
(2) The CEMP must—
(a) be substantially in accordance with the outline construction environmental management plan certified under article 45 (certification of plans etc.);
(b) contain a record of all the sensitive environmental features that have the potential to be affected by the construction of the proposed development;
(c) incorporate the measures referred to in the environmental statement as being incorporated in the CEMP;
(d) require adherence to working hours of 07:30 to 19:30 on Mondays to Saturdays from 1 March to 31 October, 07:30 to 18:00 on Mondays to Saturdays from 1 November to 28 February and 08:00 to 13:00 on Sundays, except for—
(i) traffic management activities;
(ii) bridge beam lifts;
(iii) demolition operations requiring the full or partial temporary closure of roads;
(iv) surfacing works at tie-in locations;
(v) importation of materials during peak holiday seasons;
(vi) the provision of services at compounds, including CCTV and vehicle recovery;
(vii) any emergency works; and
(viii) any works for which different working hours have been agreed with parties who will or may be affected by those works and recorded in the approved CEMP, in which case the CEMP must require adherence to those working hours.
(3) The authorised development must be constructed in accordance with the approved CEMP.
(4) Upon completion of construction of the authorised development the CEMP must be converted into the HEMP. The HEMP must be submitted to the Secretary of State for approval within 28 days of the opening of the authorised development for public use.
(5) The authorised development must be operated and maintained in accordance with the HEMP approved under paragraph (4).

---
Source: https://www.legislation.gov.uk/uksi/2020/121/schedule/2/paragraph/3 (the official version)
Page: https://openlegislation.uk/a30-chiverton-to-carland-cross-development-consent-order-2020/schedule-2/paragraph-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.