# The A30 Chiverton to Carland Cross Development Consent Order 2020, Paragraph 27


(1) Following construction of the over-run areas comprised within Work No. 4 and Work. No. 5, the undertaker will at its own cost and expense and insofar as it is the owner of and/or the highway authority for the areas in question—
(a) keep the over-run areas clear of, without limitation, all rubbish, debris and vehicles, at all times;
(b) undertake any clearance and/or maintenance required within reasonable timescales;
(c) provide ScottishPower Renewables with copies of keys required to unlock any lockable bollards or similar that would prevent or hinder the use of the over-run areas; and
(d) restrict access to those parts of the over-run areas where lockable bollards or similar are in place to the undertaker, the local highway authority and to ScottishPower Renewables only.
(2) In the event that the existing re-aligned A30 is adopted the undertaker will use reasonable endeavours to procure that the local highway authority complies with the obligations under paragraph (1).

---
Source: https://www.legislation.gov.uk/uksi/2020/121/schedule/9/paragraph/27 (the official version)