# The A38 Derby Junctions Development Consent Order 2023, Schedule 5: LAND IN WHICH ONLY NEW RIGHTS ETC. MAY BE ACQUIRED


(1)
(2)
(3)
Plot reference number shown on land plans
Purpose for which rights over land may be acquired
Relevant part of the authorised development
Land Plans – Sheet 1
1/3a
Required for the establishment and maintenance of environmental mitigation and enhancement areas
Work No. 8
1/3b
Required for the establishment and maintenance of environmental mitigation and enhancement areas and the diversion and maintenance of and access to utilities and the establishment and maintenance of flood storage areas
Work No. 1, 8 and 9
1/4b
Required for the establishment of environmental mitigation and enhancement and the diversion and maintenance of and access to utilities
Work No. 8 and 9
Land Plans – Sheet 2
2/1b
Required for the diversion and maintenance of and access to utilities and the establishment and maintenance of environmental mitigation and enhancement
Work No. 8 and 9
2/1c
Required for the construction of a diverge slip road and for the establishment of environmental mitigation and enhancement areas and the construction of highway drainage attenuation
Work No. 2 and 8
2/1f
Required for the construction of a cycle track and the diversion and maintenance of and access to utilities
Work No. 3 and 9
2/1o
Required for the construction and reconfiguration of the junction between Lyttelton Street and Kingsway Park Close and the diversion and maintenance and access to utilities
Work No. 7 and 9
2/1p
Required for the construction and reconfiguration of the junction between Lyttelton Street and Kingsway Park Close and the diversion and maintenance and access to utilities
Work No. 7 and 9
2/7a and 2/8
Required for the diversion construction and maintenance of a cycle track
Work No. 3
2/9
Required for the construction and maintenance of a cycle track and the diversion and maintenance of and access to utilities
Work No. 3 and 9
2/13a
Required to construct a link road and the diversion and maintenance and access to utilities
Work No. 7 and 9
2/19a
Required to construct a link road and the diversion and maintenance of and access to utilities and the construction of footways
Work No. 7 and 9
2/19b
Required to construct a link road and the diversion and maintenance of and access to utilities and the reconfiguration of Lyttelton junction
Work No. 7 and 9
Land Plans – Sheet 3
3/1p and 3/1q
Required for the construction of a northbound diverge slip road and the diversion and maintenance of and access to utilities and the stopping up of the Enfield Road entry and exit roads
Work No. 11 and 22
3/1w and 3/1x
Required for the diversion and maintenance of and access to a utility corridor and construction of a new emergency access
Work No. 16 and 21
3/5a
Required for the alteration, realignment and grading of highway; the construction, improvement and realignment of cycle track and the diversion and maintenance of and access to utilities
Work No. 10, 15 and 22
3/9b
Required for alterations to the access to and egress from the filling station and fast-food site and the diversion and maintenance of utilities
Work No. 16 and 22
3/16a, 3/17 and 3/19
Required for the construction and alteration of a private means of access
Work No. 16
3/22b
Required for the construction of a southbound diverge slip and alteration realignment and grading of highway and the construction and maintenance of a noise barrier and alterations to the access to and egress from the A52 to the Royal School for the Deaf
Work No. 13 and 16
Land Plans – Sheet 4
4/1b
Required for the diversion and maintenance of and access to a utility corridor and for the demolition of a footbridge and replacement of a footbridge
Work No. 10 and 21
4/1d
Required for the alteration, realignment and grading of a highway
Work No. 10, 21 and 22
4/7b
Required for the construction and maintenance of a noise barrier
Work No. 13
Land Plans – Sheet 6
6/2
Required for the construction and maintenance of a flood plain compensation area and the diversion and maintenance of and access to utilities
Work No. 31
Land Plans – Sheet 7
7/5
Required for the construction and maintenance of a flood plain compensation area and the diversion and maintenance of and access to utilities
Work No. 31
Land Plans – Sheet 8
8/6
Required for the access construction and maintenance of a railbridge
Work No. 23
8/23b, 8/25c and 8/21
Required for the diversion and maintenance of and access to utilities
Work No. 35
Land Plans – Sheet 9
9/6b
Required for the alteration, realignment and grading of northbound and southbound carriageways, the construction of a southbound diverge slip road and the diversion and maintenance of and access to utilities
Work No. 23, 26 and 35

---
Source: https://www.legislation.gov.uk/uksi/2023/923/schedule/5 (the official version)