# The A417 Missing Link Development Consent Order 2022, Article 25: Compulsory acquisition of land – incorporation of the mineral code


Parts 2 and 3 of Schedule 2 (minerals) to the Acquisition of Land Act 1981 are incorporated into this Order subject to the modifications that—
(a) paragraph 8(3) is not incorporated;
(b) for “the acquiring authority” substitute “the undertaker”; and
(c) for “undertaking” substitute “authorised development”.

---
Source: https://www.legislation.gov.uk/uksi/2022/1248/article/25 (the official version)
Page: https://openlegislation.uk/a417-missing-link-development-consent-order-2022/article-25
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.