# The A417 Missing Link Development Consent Order 2022, Paragraph 4


Part 1 of the 1965 Act, as applied by section 125 (application of compulsory acquisition provisions) of the 2008 Act (and modified by article 30 (modification of Part 1 of the 1965 Act)) to the acquisition of land under article 24 (compulsory acquisition of land), applies to the compulsory acquisition of a right by the creation of a new right, or to the imposition of a restrictive covenant under article 27(1) (compulsory acquisition of rights and restrictive covenants)—
(a) with the modifications specified in paragraph 5; and
(b) with such other modifications as may be necessary.

---