# The A428 Black Cat to Caxton Gibbet Development Consent Order 2022, Paragraph 67

Extent: E+W

The undertaker must no later than 28 days from the date that the plans and documents submitted to and certified by the Secretary of State in accordance with article 48 (certification of documents, etc.) are certified by the Secretary of State, provide a set of those plans and documents to Network Rail in an agreed electronic read only format.

---
Source: https://www.legislation.gov.uk/uksi/2022/934/schedule/9/paragraph/67 (the official version)
Page: https://openlegislation.uk/a428-black-cat-to-caxton-gibbet-development-consent-order-2022/schedule-9/paragraph-67
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.