# The A46 Newark Bypass Development Consent Order 2025, Article 7: Application of the 1990 Act

Extent: E+W

(1) This article applies where the Order land is used for the temporary works.
(2) Where this article applies, section 57(2) (planning permission required for development) of the 1990 Act applies as if the development consent granted by this Order were planning permission granted for a limited period.
(3) In this article, “the temporary works” means—
(a) those works described for Work Nos. 10 to 11, 21, 25, 28, 47, 59, 65, 68, 85, 92, 106 and 126 to 128 in Schedule 1; or
(b) temporary works carried out as part of “other associated development” in connection with the Work Nos. in Schedule 1.

---
Source: https://www.legislation.gov.uk/uksi/2025/1090/article/7 (the official version)
Page: https://openlegislation.uk/a46-newark-bypass-development-consent-order-2025/article-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.