# The A46 Newark Bypass Development Consent Order 2025, Schedule 7: LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

Extent: E+W

(1)
Plot reference number shown on Land Plans
(2)
Purpose for which temporary possession may be taken
(3)
Relevant part of the authorised development
Land Plans – Sheet 1
1/1n
Temporary access and working area to facilitate the temporary diversion of Newark Bridleway No. 2.
Work No. 3
1/5e
Temporary access and working room to facilitate Work No. 6.
Work No. 6
1/5f
Temporary access to implement new road signage.
Ancillary
1/5l
Temporary access to the river for deploying safety boat in association with Work No. 7.
Work No. 7
1/5p
Temporary access for the construction of a new bridge to carry the A46 over the River Trent, including deployment of a safety boat in association with Work No. 7.
Work No. 7
1/5q
Temporary access and works to facilitate the temporary diversion of Newark Bridleway No. 2.
Work No. 3
1/7a
Temporary working space to tie in with the construction of the new Farndon Roundabout.
Ancillary
1/10a
Temporary works area and access to facilitate the construction of the new Farndon Roundabout.
Work No. 10
1/10b
Temporary access and works to facilitate the temporary diversion of Newark Bridleway No. 2.
Work No. 3
1/12a
Temporary access and works to facilitate the temporary diversion of Newark Bridleway No. 2.
Work No. 3
1/12b
Temporary access and works to facilitate the temporary diversion of Newark Bridleway No. 2.
Work No. 3
1/13a
Temporary storage, welfare unit and access to Work Nos. 6 and 7; and temporary access and works to facilitate the temporary diversion of Newark Bridleway No. 2.
Work Nos. 3, 6, 7 and 127
1/14a
Temporary access and works to facilitate the temporary diversion of Newark Bridleway No. 2.
Work No. 3
1/14b
Temporary access and works to facilitate the temporary diversion of Newark Bridleway No. 2.
Work No. 3
1/14c
Access to Work No. 3 to accommodate bridleway diversion.
Work No. 3
1/15a
Temporary access and works to facilitate the temporary diversion of Newark Bridleway No. 2.
Work No. 3
1/17a
Temporary storage, welfare unit and access to Work Nos. 6 and 7; and temporary access and works to facilitate the temporary diversion of Newark Bridleway No. 2.
Work No. 3, 6, 7 and 127
1/18a
Temporary access to the river for deploying safety boat in association with Work No. 7.
Work No. 7
1/18d
Temporary access to the river for deploying safety boat in association with Work No. 7.
Work No. 7
Land Plans – Sheet 2
2/2j
Temporary access for the construction of a new bridge to carry the A46 over the railway line; temporary access for monitoring the railway line in association with Work No. 26; diversion of 11kV electricity distribution cables to underground buried cable; and diversion of electronic communications equipment.
Work Nos. 26, U3 and U4
2/2k
Temporary access for the construction of a new bridge to carry the A46 over the railway line; and temporary access for monitoring the railway line in association with Work No. 26.
Work No. 26
2/2m
Temporary access for the construction of a new bridge to carry the A46 over the railway line; temporary access for monitoring the railway line in association with Work No. 26; diversion of 11kV electricity distribution cables to underground buried cable; and diversion of electronic communications equipment.
Work No. 26, U3 and U4
2/2p
Temporary access to Work No. 27.
Work No. 27
2/3a
Temporary working room for Work Nos. 22 and 24.
Work Nos. 22 and 24
2/5a
Temporary access for clearing of Old Trent Dyke for installation of Work No. 23.
Work No. 23
2/5b
Temporary access for clearing of Old Trent Dyke for installation of Work No. 23.
Work No. 23
2/7a
Temporary storage, welfare unit and access to facilitate construction of access tracks, the A46 dual carriageway and a new bridge to carry the A46 over the railway line.
Work Nos. 28, 26, 4 and 29
2/7c
Temporary access to Work No. 4.
Work No. 4
Land Plans – Sheet 3
3/1u
Temporary works area to facilitate widening of railway line to facilitate A46 construction.
Work No. 58
3/2e
Temporary construction compound.
Work No. 53
3/2ff
Access for monitoring railway line in association with Work No. 58.
Work No. 58
3/2g
Temporary working area for alteration of the B6326 Great North Road to tie-in to the Cattle Market Junction Circulatory.
Work No. 49
3/2g4
Temporary working area for alteration of the B6326 Great North Road to tie-in to the Cattle Market Junction Circulatory.
Work No. 49
3/2gg
Access for monitoring railway line in relation to Work No. 58.
Work No. 58
3/2nn
Temporary access to Work No. 4.
Work No. 4
3/2r
Temporary access to Work No. 32.
Work No. 32
3/2x
Temporary Access for monitoring railway line in relation to Work No. 58.
Work No. 58
3/4e
Temporary working space for environmental mitigation and access to utilities.
Ancillary
3/7a
Access to Work No. 4.
Work No. 4
3/10d
Temporary working area for environmental mitigation works.
Environmental Mitigation
3/11a
Temporary construction compound.
Work No. 53
3/11c
Temporary working area for alteration of the B6326 Great North Road to tie-in to the Cattle Market Junction Circulatory.
Work No. 49
3/11e
Temporary construction compound.
Work No. 53
3/13a
Working area for environmental mitigation works.
Environmental Mitigation
3/14a1
Temporary working area and access for turning circle for works vehicles.
Ancillary
3/14b1
Access and working room to facilitate the construction of Work No. 51
Work No. 51
3/14h
Access to Work No. 49; and temporary working space for environmental mitigation.
Work No. 49
Environmental Mitigation
Land Plans – Sheet 4
4/2e
Temporary access for the construction of a new bridge to carry the A46 over the River Trent and a temporary bridge to accommodate movement of plant and materials to temporary compound; and temporary access for construction of attenuation basins and drainage infrastructure.
Work Nos. 63, 64 and 67
4/2g
Access for deployment of safety boat in the River Trent and working area associated with Work No. 64.
Work No. 64
4/2k
Access for deployment of safety boat in the River Trent and working area associated with Work No. 64.
Work No. 64
4/2o
Access for deployment of safety boat in the River Trent and working area associated with Work No. 64.
Work No. 64
4/2p
Access for deployment of safety boat in the River Trent and working area associated with Work No. 64.
Work No. 64
4/2q
Access for deployment of safety boat in the River Trent and working area associated with Work No. 64.
Work No. 64
4/5d
Temporary access to Work No. 71.
Work No. 71
4/5h
Temporary access for the construction of a new bridge to carry the A46 over the River Trent; temporary works area, welfare unit and access to facilitate the construction of a new bridge parallel to Nether Lock Viaduct; and access for monitoring railway line in relation to Work Nos. 64 and 65.
Work Nos. 64 and 65
4/7g
Temporary works area, welfare unit and access to facilitate the construction of a new bridge parallel to Nether Lock Viaduct.
Work No. 65
4/7h
Temporary construction compound.
Work No. 71
4/7i
Temporary construction compound.
Work No. 71
4/8a
Temporary construction compound and access between construction compound and works.
Work Nos. 62 and 63
4/8c
Temporary construction compound.
Work No. 71
4/11a
Temporary access to Work No. 71.
Work No. 71
Land Plans – Sheet 5
5/1d
Working room and access to tie in with new roundabout layout.
Ancillary
5/1m
Working room and access to tie in with new roundabout layout.
Ancillary
5/3d
Access for potential reprofiling of drainage ditches.
Ancillary
5/3h
Working room and access to tie in with new roundabout layout.
Ancillary
5/3i
Working room and access to tie in with new roundabout layout.
Ancillary
5/3j
Access for potential reprofiling of drainage ditches.
Ancillary
5/7d
Temporary working space for environmental mitigation.
Ancillary
5/8a1
Temporary working space for environmental mitigation.
Ancillary
5/17d
Temporary construction compound and laydown area.
Work Nos. 114 and 106
Land Plans – Sheet 6
6/1c
Temporary working space for environmental mitigation.
Ancillary
6/2b
Temporary working space for environmental mitigation.
Ancillary
6/2d
Temporary working space for environmental mitigation.
Ancillary
6/4b
Temporary working space and access to facilitate realignment of Drove Lane and tie into the new Winthorpe Roundabout.
Work No. 115
6/6a1
Temporary working space for environmental mitigation.
Ancillary
6/6c
Temporary storage and lay-down area to facilitate construction of the new Winthorpe Roundabout.
Work No. 111
6/6c1
Temporary working space for environmental mitigation.
Ancillary
6/6d
Temporary working space for environmental mitigation.
Ancillary
6/7c
Temporary storage, lay-down area, access and working area to facilitate construction of the new Winthorpe Roundabout and the construction of a temporary access track.
Work Nos. 120 and 117
6/8a
Temporary access for construction of new signage.
Work No. 121
Land Plans – Sheet 7
7/2b
Temporary access and working room to facilitate the construction of an access track and floodplain compensation area.
Work Nos. 122 and 125

---
Source: https://www.legislation.gov.uk/uksi/2025/1090/schedule/7 (the official version)
Page: https://openlegislation.uk/a46-newark-bypass-development-consent-order-2025/schedule-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.