# The A46 Newark Bypass Development Consent Order 2025, Paragraph 72: Capitalised sums

Extent: E+W

Any capitalised sum which is required to be paid under this Part must be calculated by multiplying the cost of the maintenance or renewal works to the waterway necessitated as a result of the operation of the authorised development by the number of times that the maintenance or renewal works will be required during the operation of the authorised development.

---
Source: https://www.legislation.gov.uk/uksi/2025/1090/schedule/9/paragraph/72 (the official version)
Page: https://openlegislation.uk/a46-newark-bypass-development-consent-order-2025/schedule-9/paragraph-72
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.