# The A500 Trunk Road (Stoke Pathfinder Project) and Slip Roads Order 2003, Article 2


In this Order—
(1) all measurements of distance are measured along the route of the relevant highway;
(2) (i) “the main new road” means the new highway which the Secretary of State proposes to construct along the route described in Schedule 1 to this Order;
(ii) “the new trunk roads” means the main new road and the slip roads;
(iii) “the plan” means the plan marked “The A500 Trunk Road (Stoke Pathfinder Project) and Slip Roads Order 2003” comprised in plan Folio numbered HA/14/0D/381. signed by authority of the Secretary of State for Transport and deposited at DfT Records Management Branch, Ashdown House, St Leonards on Sea, Hastings, East Sussex TN37 7GA; and
(iv) “the slip roads” means the new highways which the Secretary of State proposes to construct along the routes described in Schedule 2 to this Order and which connect the main new road with other highways or proposed highways at the places stated in that Schedule.

---
Source: https://www.legislation.gov.uk/uksi/2003/1601/article/2 (the official version)
Page: https://openlegislation.uk/a500-trunk-road-stoke-pathfinder-project-and-slip-roads-order-2003/article-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.