# The A57 Link Roads Development Consent Order 2022, Part 1: PUBLIC RIGHTS OF WAY AND HIGHWAYS TO BE STOPPED UP AND FOR WHICH A SUBSTITUTE IS TO BE PROVIDED

Extent: E+W+S

(1)
Public right of way or highway to be stopped up
(2)
Extent of stopping up
(3)
New highway to be substituted/provided
Footpath LON/90/100
For a distance of 60 metres between points 6/4 and 6/5 as shown on Sheet 6 of the streets, rights of way and access plans
New footpath heading south east from points 6/3 to 6/1 on Sheet 6 of the streets, rights of way and access plans.
Footpath LON/88/60
For a distance of 210 metres between point 9/2 on Sheet 9 and point 5/2 on Sheet 5 of the streets, rights of way and access plans
New footpath from point 9/2 on Sheet 9 to point 5/2 on Sheet 5 of the streets, rights of way and access plans.
Footpath LON/87/10
For a distance of 160 metres between points 4/14 on Sheet 4 and point 8/11 on Sheet 8 of the streets, rights of way and access plans
Proposed footpath will connect directly onto the new A57 Link Roads ‘Mottram Moor Junctions’ footway (south west corner) via points 4/19, 4/a and 4/18 to point 8/11.
Footpath LON/52/10
For a distance of 230 metres between points 2/5 and 2/4 on Sheet 2 of the streets, rights of way and access plans
New footpath connection from points 2/5 to 2/8, new combined footway/cycleway with equestrian use between points 2/8 and 2/6 and new footpath between points 2/6 and 2/4 on Sheet 2 of the streets, rights of way and access plans.
Footpath LON/51/20
For a distance of 100 metres between points 2/3 and 2/4 on Sheet 2 of the streets, rights of way and access plans
New combined footway/cycleway with equestrian use connecting points 2/3 to 2/6 and new footpath between points 2/6 and 2/4 on Sheet 2 of the streets, rights of way and access plans.
Footpath LON/50/10
For a distance of 160 metres between points 1/42 and 1/44 on Sheet 1 of the streets, rights of way and access plans
New footpath link provided to new combined footway/cycleway with equestrian use between points 1/42 and 1/43.
The new combined footway/cycleway with equestrian use will connect points 1/43 and 1/7, a diversion will then use the new combined footway/cycleway provision at the M67 Junction 4, leaving at point 1/19 and then using the existing footway to reach point 1/8 of the new combined footway/cycleway with equestrian use, which then links back to point 1/44.
An alternative is to travel along the new bridleway between points 1/43 and 2/8 using the proposed Old Mill underpass and travelling past points 2/6 to 1/44.
Footpath LON/52/20
For a distance of 380 metres between points 1/45 on Sheet 1 and point 2/4 on Sheet 2 of the streets, rights of way and access plans
New footpath link provided between points 2/7 and 2/6 with the new combined footway/cycleway with equestrian use connecting point 2/6 on Sheet 2, point 1/44 on Sheet 1 and point 1/8 on Sheet 1 of the streets, rights of way and access plans.
Footway along north eastern corner of the M67 Junction 4 roundabout
For a distance of 135 metres between points 1/4 and 1/19 on Sheet 1 of the streets, rights of way and access plans
New combined footway/cycleway from point 1/4 to 1/1 to 1/26 to 1/25 to 1/24 to 1/23 to 1/21 and 1/19 on Sheet 1 of the streets, rights of way and access plans.
Footway/Shared User Path/crossing along the southern edge of the M67 Junction 4 roundabout
For a distance of 49 metres between points 1/17 and 1/16 on Sheet 1 of the streets, rights of way and access plans
New combined footway/cycleway from points 1/15 to 1/14 on Sheet 1 of the streets, rights of way and access plans.
Footway/Shared User Path/crossing along the western edge of the M67 Junction 4 roundabout
For a distance of 52 metres between points 1/38 and 1/37 on Sheet 1 of the streets, rights of way and access plans
New combined footway/cycleway from points 1/1 to 1/27 on Sheet 1 of the streets, rights of way and access plans.
Footway/crossing
For a distance of 25 metres between points 1/6 and 1/19 on Sheet 1 of the Street, Rights of Way and Access Plans
New combined footway/cycleway from point 1/20 to 1/21 to 1/19 on Sheet 1 of the streets, rights of way and access plans.
Footway/crossing
For a distance of 340 metres between point 4/15 on Sheet 4 and point 8/10 on Sheet 8 of the streets, rights of way and access plans
New combined footway/cycleway from point 4/21 to 4/22 to 4/23 on Sheet 4 of the streets, rights of way and access plans and new combined footway/cycleway with equestrian use from points 4/23 to 4/17 and then on combined footway cycleway from point 4/17 to point 8/10 on Sheet 8 of the streets, rights of way and access plans.
Footway/crossing
For a distance of 45 metres between points 4/13 to 4/12 on Sheet 4 of the streets, rights of way and access plans
New combined footway/cycleway from points 4/19 to point 4/9 on the streets, rights of way and access plans.

---
Source: https://www.legislation.gov.uk/uksi/2022/1206/schedule/4/part/1 (the official version)
Page: https://openlegislation.uk/a57-link-roads-development-consent-order-2022/schedule-4/part-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.