# The A585 Windy Harbour to Skippool Highway Development Consent Order 2020, Schedule 7: LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN


(1)
Plot Reference Number shown on Land Plans
(2)
Purpose for which temporary possession may be taken
(3)
Relevant part of the authorised development
Land Plans – Sheet 1
1/07a, 1/07f, 1/07l
Required to provide construction working area for replacement culvert and for the diversion of electric cables and associated auxiliary cables
Work No.6
Work No.115
1/05a, 1/05b
Required to provide construction working area for replacement culvert and dwarf wall and for the diversion of a water pipeline
Work No.34
Work No.115
Work No.122
1/05c
Required for the provision of the main site compound to include, but not limited to, site offices, welfare facilities, parking provisions, storage of plant and materials and the treatment of site generated waste
All Works
1/05d
Required to provide construction working area for the combined footway/cycleway and for the diversion of a water pipeline
Work No.17
Work No.34
1/30a, 1/34a
Required to provide an improved private means of access and for the diversion of a water pipeline and for the diversion of electric cables and associated auxiliary cables
Work No.23
Work No.24
Work No.30
Work No.31
1/30b, 1/34b, 1/34f, 1/34g
Required for the diversion of a water pipeline and for the diversion of electric cables and associated auxiliary cables
Work No.24
Work No.30
Work No.31
Land Plans – Sheet 3
3/01a
Required to provide a construction working area and improved private means of access
Work No.97
Land Plans – Sheet 4
4/02c
Required to provide a construction working area for highway boundary fencing and for the diversion of electric cables and associated auxiliary cables
Work No.36
Work No.40
4/02b, 4/02c, 4/03a, 4/02d, 4/06c, 4/06d, 4/06h, 4/06e, 4/06g, 4/08b, 4/08e, 4/08g
Required to provide a construction working area for highway boundary fencing
Work No.40
4/06d. 4/06h, 4/06g
Required to provide a construction working area for highway boundary fencing and for the diversion of electric cables and associated auxiliary cables
Work No.40
Work No.42
4/06f
Required to provide a flood mitigation area
Work No.98
4/08a
Required to provide a flood mitigation area
Work No.111
4/08d
Required to provide a flood mitigation area
Work No.110
4/08f
Required to provide a flood mitigation area
Work No.109
4/08l
Required to provide a construction working area and for drainage works
Work No.113
4/10a, 4/12
Required for the provision of the main site compound to include, but not limited to, site offices, welfare facilities, parking provisions, storage of plant and materials and the treatment of site generated waste
All Works
Land Plans – Sheet 5
5/01a
Required to provide a construction working area (including for construction material storage, construction access and storage of plant) and for the diversion of water pipelines
All Works
5/01c
Required to provide a construction working area for highway boundary fencing and for the diversion of a water pipeline
Work No.48
Work No.53
Work No.55
Work No.58
5/01e
Required to provide a temporary access for main construction compound
All Works
5/01f, 5/01k, 5/01i
Required to provide a construction working area for highway boundary fencing
Work No.57
Work No.58
Work No.59
5/01h, 5/06j
Required for the diversion of a water pipeline and construction working area for culvert
Work No.61
Work No.62
5/05b
Required for the diversion of a water pipeline
Work No.60
5/06a
Required to provide a borrow pit area and for the diversion of electric cables and associated auxiliary cables and water pipeline
Work No.63
Work No.61
Work No.64
5/06c
Required to provide a construction working area for highway boundary fencing and for the diversion of water pipelines and electric cables and associated auxiliary cables
Work No.58
Work No.59
Work No.61
5/06i
Required to provide a construction working area for the bridge and for the diversion of electric cables and associated auxiliary cables
Work No.58
Work No.70
Work No.64
5/06d
Required to provide a construction working area for highway boundary fencing and for the diversions of water pipelines and electric cables and associated auxiliary cables
Work No.58
Work No.60
Work No.61
Work No.72
5/06b
Required to provide a borrow pit area and for the diversion of electric cables and associated auxiliary cables and for diversion of a gas pipeline and for the diversion of water pipelines
Work No.60
Work No.61
Work No.69
Work No.72
Work No.78
5/06h
Required to provide a construction working area for the bridge and for the diversion of electric cables and associated auxiliary cables and gas pipeline
Work No. 69
Work No.70
Work No.72
5/07c, 5/15a
Required for the diversion of a water pipeline
Work No.61
5/12
Required to provide an improved private means of access and for the diversion of a gas pipeline
Work No.67
Work No.68
5/15, 5/07b, 5/07d
Required for the diversion of a water pipeline
Work No.60
5/09e, 5/09c, 5/09d, 5/09b
Required to provide an improved private means of access and for the diversion of electric cables and associated auxiliary works and for the diversion of a gas pipeline and for the diversion for telecommunications cables
Work No.71
Work No.72
Work No.73
Work No.74
Work No.75
Work No.76
Work No.120
Land Plans – Sheet 6
6/43a
Required to provide a construction working area for highway boundary fencing
Work No.87
Land Plans – Sheet 7
7/01a
Required to provide a construction working area for highway boundary fencing
Work No.58
7/02d
Required to provide a construction working area for highway boundary fencing and for the diversion of a water pipeline
Work No.58
Work No.77
7/06b, 7/06c, 7/08a, 7/07a
Required to provide a construction working area for highway boundary fencing
Work No.58
Work No.90
Work No.93
7/07b, 7/07c
Required to provide a construction working area for highway boundary fencing and pavement widening
Work No.58
7/04a
Required to provide a construction working area for highway boundary fencing and culvert
Work No.58
Work No.91
Land Plans – Sheet 8
8/02d
Required to provide a construction working area for highway boundary fencing
Work No.29
8/02e, 8/04
Required to provide a habitat mitigation area
All Works

---
Source: https://www.legislation.gov.uk/uksi/2020/402/schedule/7 (the official version)
Page: https://openlegislation.uk/a585-windy-harbour-to-skippool-highway-development-consent-order-2020/schedule-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.