# The A63 (Castle Street Improvement, Hull) Development Consent Order 2020, Paragraph 14: Earl de Grey public house

Extent: E+W

(1) None of the works to the Earl de Grey public house set out in Schedule 1, Work No.30 are to commence until—
(a) details of the reconstruction or partial reconstruction of the building; and
(b) a method statement describing full details of how the Earl de Grey public house is to be—
(i) structurally assessed;
(ii) recorded in situ to level 4 building recording in accordance with Historic England guidance;
(iii) dismantled, including compiling an inventory of all building materials to be re-used, and justification for excluding any historic fabric;
(iv) stored; and
(v) reconstructed; and
(c) a timetable for the completion of the work listed under part (b),
have been submitted to and approved in writing by the Secretary of State, following consultation with the relevant planning authority and Historic England on matters related to their functions.
(2) The works to the Earl de Grey public house must be carried out in accordance with the approved details unless the Secretary of State, following consultation with the relevant planning authority and Historic England on matters related to their functions gives consent to a variation.

---
Source: https://www.legislation.gov.uk/uksi/2020/556/schedule/2/paragraph/14 (the official version)
Page: https://openlegislation.uk/a63-castle-street-improvement-hull-development-consent-order-2020/schedule-2/paragraph-14
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.