# The A63 (Castle Street Improvement, Hull) Development Consent Order 2020, Paragraph 17: High Street underpass works

Extent: E+W

(1) Work No.41 is not to commence until the following details of the improvements to the High Street underpass have been submitted to and approved in writing by the Secretary of State, following consultation with the relevant planning authority on matters related to its function—
(a) design;
(b) materials;
(c) hard and soft landscaping;
(d) means of enclosure;
(e) lighting;
(f) wayfinding and interpretation;
(g) public art which for the avoidance of doubt shall not include the use of paint on any highway structures and shall not be visible to drivers on the A63;
(h) CCTV.
(2) The underpass improvement works must be undertaken before the commencement of any of Works numbers 35, 36, 37, 38, 39, or 40 as set out within Schedule 1, and in accordance with the approved details, unless the Secretary of State, following consultation with the relevant planning authority on matters related to its function, gives consent to any variation.

---
Source: https://www.legislation.gov.uk/uksi/2020/556/schedule/2/paragraph/17 (the official version)
Page: https://openlegislation.uk/a63-castle-street-improvement-hull-development-consent-order-2020/schedule-2/paragraph-17
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.