# The A66 Northern Trans-Pennine Development Consent Order 2024, Paragraph 13: A 155 metre length of improved A6 (northbound approach to Kemplay Bank Roundabout)

Extent: E+W

A length of improved highway to be classified as part of the A6, commencing from a point 182 metres to the south-west of the existing Penrith Community Fire Station, and following the existing alignment of the A6 for a distance of 155 metres, to its junction with the new Kemplay Bank Roundabout, identified by a green line on the classification of roads plan for scheme 0102.

---