# The A66 Northern Trans-Pennine Development Consent Order 2024, Paragraph 62: A66 all-purpose dual carriageway

Extent: E+W

A 3.6 km length of new road to be constructed and classified as part of the A66 trunk road all-purpose dual carriageway (such length also including existing highway to be improved) commencing from a point 550 metres to the west of the Clint Lane Overbridge and following the existing A66 alignment for a distance of 3.6 km in a generally easterly direction to a point 363 metres east of the access to Hulands Quarry, identified by a red line on the classification of roads plan for scheme 07.

---
Source: https://www.legislation.gov.uk/uksi/2024/360/schedule/7/paragraph/62 (the official version)
Page: https://openlegislation.uk/a66-northern-trans-pennine-development-consent-order-2024/schedule-7/paragraph-62
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.