# The Abergelli Power Gas Fired Generating Station Order 2019, Paragraph 29: Co–operation

Extent: E+W+S

National Grid and the undertaker must each use their best endeavours to co–ordinate with the other party on the timing and method of execution of any works carried out under the Order the associated works or this Schedule (including, for the avoidance of doubt, pursuant to paragraph 22(2) and paragraph 24 or 25) or any works required by National Grid in respect of their apparatus within and adjoining the Order land in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of National Grid’s undertaking.

---
Source: https://www.legislation.gov.uk/uksi/2019/1268/schedule/11/paragraph/29 (the official version)
Page: https://openlegislation.uk/abergelli-power-gas-fired-generating-station-order-2019/schedule-11/paragraph-29
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.