# The Abergelli Power Gas Fired Generating Station Order 2019, Paragraph 51: Acquisition of land

Extent: E+W+S

Regardless of any provision in this Order or anything shown on the land plans or contained in the book of reference to the Order the undertaker must not acquire any apparatus or extinguish any easement or other interest of the solar operator otherwise than by agreement (such agreement not to be unreasonably withheld).

---
Source: https://www.legislation.gov.uk/uksi/2019/1268/schedule/11/paragraph/51 (the official version)