# The Abergelli Power Gas Fired Generating Station Order 2019, Paragraph 61: Acquisition of Land

Extent: E+W+S

Regardless of any provision in this Order or anything shown on the land plans or contained in the book of reference to the Order, the undertaker must not acquire any land interest or apparatus or override any easement or other interest of the protected person otherwise than by agreement (such agreement not to be unreasonably withheld).

---
Source: https://www.legislation.gov.uk/uksi/2019/1268/schedule/11/paragraph/61 (the official version)
Page: https://openlegislation.uk/abergelli-power-gas-fired-generating-station-order-2019/schedule-11/paragraph-61
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

