(1) Numbered work 5 of the authorised development must not commence until a dust management plan covering that numbered work has been submitted to and approved in writing by the relevant planning authority, in consultation with Natural Resources Wales. The dust management plan must be substantially in accordance with the contents outlined in the outline construction environmental management plan and must include details of a complaints procedure.
(2) All construction works must be undertaken in accordance with the approved dust management plan.

---