# The Abergelli Power Gas Fired Generating Station Order 2019, Paragraph 22: Construction staff travel plan

Extent: E+W+S

(1) The authorised development must not commence until a travel plan for construction workers has been submitted to and approved by the relevant planning authority. The travel plan must be substantially in accordance with the outline construction staff travel plan.
(2) The travel plan must be carried out as approved during construction of the authorised development.

---
Source: https://www.legislation.gov.uk/uksi/2019/1268/schedule/2/paragraph/22 (the official version)