# The Abergelli Power Gas Fired Generating Station Order 2019, Paragraph 24: Dates of final commissioning, completion of construction and cessation

Extent: E+W+S

(1) The undertaker must notify the relevant planning authority in writing of the date of final commissioning as soon as reasonably practicable and in any event within three months after the occurrence of that date.
(2) The undertaker must notify the relevant planning authority in writing of the date of completion of construction as soon as reasonably practicable and in any event within three months after the occurrence of that date.
(3) The undertaker must notify the relevant planning authority in writing of the date the authorised development permanently ceases to generate power on a commercial basis as soon as reasonably practicable and in any event within three months after the occurrence of that date.

---
Source: https://www.legislation.gov.uk/uksi/2019/1268/schedule/2/paragraph/24 (the official version)
Page: https://openlegislation.uk/abergelli-power-gas-fired-generating-station-order-2019/schedule-2/paragraph-24
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.