# The Abergelli Power Gas Fired Generating Station Order 2019, Paragraph 25: Control of noise during operational phase

Extent: E+W+S

(1) Following the date of final commissioning, site–attributable noise arising from the operation of numbered work 1 must be limited at all times of day to the noise levels set out in column A of Table 3 measured at the coordinates set out in column B of Table 3—
Table 4
A
B
B
Daytime Noise Limit BS 4142:2014 rating level (dB LAR)
Night Time Noise Limit BS 4142:2014 rating level (dB LAR)
Location
Coordinates X
Coordinates Y
45
39
Cefn–betingau
266046
201482
41
40
Maes–Eglwys
265438
200654
48
43
Lletty’r Morfil Farm
264747
201105
45
41
Abergelli Farm
265125
201643
(2) Noise measurements at or in close proximity to each of the identified locations must be undertaken in accordance with British Standard 7445 and submitted by the undertaker to the relevant planning authority within a three month period beginning with the date of final commissioning, including details of any remedial works and a programme for implementation should noise levels exceed the level specified in Table 3 above.
(3) Any remedial works must be carried out in accordance with the approved programme for implementation and the noise measurements must be repeated and submitted to the relevant planning authority for approval following completion of remedial works to demonstrate that the noise levels are within the limits set out in Table 3 above.

---
Source: https://www.legislation.gov.uk/uksi/2019/1268/schedule/2/paragraph/25 (the official version)