# The Abergelli Power Gas Fired Generating Station Order 2019, Paragraph 7: Surface water management plan

Extent: E+W+S

(1) Numbered works 1, 2, 3 and 5 of the authorised development must not commence until, for that numbered work, a written surface water management plan has been submitted and approved in writing by the relevant planning authority. The surface water management plan must be in substantial accordance with the principles set out in the outline surface water management plan.
(2) The surface water management plan must be implemented in accordance with the approved details.

---
Source: https://www.legislation.gov.uk/uksi/2019/1268/schedule/2/paragraph/7 (the official version)
Page: https://openlegislation.uk/abergelli-power-gas-fired-generating-station-order-2019/schedule-2/paragraph-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.