# The Able Marine Energy Park Development Consent Order 2014, Article 14: Guarantees in respect of payment

Extent: E+W+S

(1) The authorised development must not be commenced and the undertaker must not begin to exercise the powers conferred by Part 5 (powers of acquisition) unless either guarantees or alternative forms of security for that purpose in respect of—
(a) the liabilities of the undertaker to pay compensation under this Order; and
(b) the liabilities of the undertaker to construct and maintain the compensatory environmental habitat referred to at paragraph 4(a) of Schedule 1 (authorised development) and any additional compensatory habitat identified in the compensation environmental management and monitoring plan,
are in place which have been approved by the relevant planning authority.
(2) A guarantee given in respect of any liability of the undertaker to pay compensation under this Order is to be treated as enforceable against the guarantor by any person to whom such compensation is payable.

---
Source: https://www.legislation.gov.uk/uksi/2014/2935/article/14 (the official version)
Page: https://openlegislation.uk/able-marine-energy-park-development-consent-order-2014/article-14
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.