# The Able Marine Energy Park Development Consent Order 2014, Article 19: Public rights of way

Extent: E+W+S

(1) With effect from the date of certification by the local highway authority that the agreed alternative right of way has been created to the standard defined in the implementation plan, the section of each public right of way (being a footpath) specified in columns (1), (2) and (3) of Schedule 5 (footpaths to be stopped up) is extinguished.
(2) With effect from that same date, the alternative section of each footpath specified in column (4) of Schedule 5 is created.
(3) In this article—
“implementation plan” means the plan referred to at requirement 11 in Schedule 11 (requirements); and
“local highway authority” has the same meaning as in section 329(1) of the 1980 Act.

---
Source: https://www.legislation.gov.uk/uksi/2014/2935/article/19 (the official version)
Page: https://openlegislation.uk/able-marine-energy-park-development-consent-order-2014/article-19
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.