# The Able Marine Energy Park Development Consent Order 2014, Article 6: Limits of deviation

Extent: E+W+S

In carrying out the authorised development the undertaker may—
(a) deviate laterally from the lines or situations of the authorised development shown on the works plans to the extent of the limits of deviation; and
(b) deviate vertically from the levels of the authorised development shown on the sections—
(i) to any extent not exceeding 1 metre upwards; or
(ii) to any extent downwards as may be found necessary or convenient.

---
Source: https://www.legislation.gov.uk/uksi/2014/2935/article/6 (the official version)