  "url": "https://openlegislation.uk/able-marine-energy-park-development-consent-order-2014/schedule-11/paragraph-12",
  "json_url": "https://openlegislation.uk/able-marine-energy-park-development-consent-order-2014/schedule-11/paragraph-12.json",
  "legislation": "uksi/2014/2935",
  "legislation_title": "The Able Marine Energy Park Development Consent Order 2014",
  "legislation_url": "https://openlegislation.uk/able-marine-energy-park-development-consent-order-2014",
  "path": "schedule/11/paragraph/12",
  "kind": "paragraph",
  "number": "12",
  "heading": null,
  "text": "(1) No stage of the authorised development is to commence until, for that stage, written details of all proposed permanent and temporary fences, walls or other means of enclosure have been submitted to and approved by the relevant planning authority.\n(2) Any temporary fencing must be removed on completion of the authorised development.\n(3) Any approved permanent fencing of the authorised development must be completed before the authorised development is brought into use.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 11 para. 12 in force at 29.10.2014, see Introductory Text"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2014/2935/schedule/11/paragraph/12",
    "retrieved_at": "2026-10-28T23:57:38.687983+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}