(1) No stage of the authorised development is to commence until a written management plan for the Killingholme North Low Lighthouse (‘the building’) has been submitted to and approved by the relevant planning authority, including the following—
(a) a structural survey to be submitted to and approved by the relevant planning authority;
(b) implementation of mitigation measures;
(c) a schedule of repair works that ensure the long-term survival of the building;
(d) an implementation timetable for all stages of work including timings to ensure that the mitigation measures and repair work are undertaken and completed in accordance with the plan;
(e) monitoring arrangements with the relevant planning authority, including notification of the commencement of work;
(f) details of all contractors to be involved in implementation of works to the building; and
(g) details of the use of the building including proposals for community access and interpretation.
(2) The management plan must be implemented as approved.

---
Source: https://www.legislation.gov.uk/uksi/2014/2935/schedule/11/paragraph/18 (the official version)
Page: https://openlegislation.uk/able-marine-energy-park-development-consent-order-2014/schedule-11/paragraph-18
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.