# The Able Marine Energy Park Development Consent Order 2014, Paragraph 22

Extent: E+W+S

(1) No stage of the authorised development is to commence until a code of construction practice for that stage has been submitted to and approved by the relevant planning authority.
(2) All construction works must be undertaken in accordance with the approved code.

---
Source: https://www.legislation.gov.uk/uksi/2014/2935/schedule/11/paragraph/22 (the official version)
Page: https://openlegislation.uk/able-marine-energy-park-development-consent-order-2014/schedule-11/paragraph-22
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.