# The Able Marine Energy Park Development Consent Order 2014, Paragraph 29

Extent: E+W+S

(1) No stage of the of the authorised development is to commence until, for that stage, after consultation with the highway authority, North East Lincolnshire Council, Royal Mail Group Ltd and Centrica plc, a construction travel plan, which must include details of the expected means of travel to and from the authorised development, road safety measures and any parking to be provided, has been submitted to and approved by the relevant planning authority.
(2) No part of the authorised development is to be brought into use until, after consultation with the highway authority and Royal Mail Group Ltd, a travel plan, which must include details of the expected means of travel to and from the authorised development and any parking to be provided, has been submitted to and approved by the relevant planning authority.
(3) The plan approved under paragraph (1) must be implemented during the construction of the authorised development and the plan approved under paragraph (2) must be implemented within one month of the authorised development being brought into use and must continue to be implemented for as long as the authorised development is used.
(4) The undertaker must have regard to any consultation response received.
(5) The plans approved under paragraphs (1) and (2) must be reviewed at least once a year or such other period as is agreed by the relevant planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2014/2935/schedule/11/paragraph/29 (the official version)
Page: https://openlegislation.uk/able-marine-energy-park-development-consent-order-2014/schedule-11/paragraph-29
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.