# The Able Marine Energy Park Development Consent Order 2014, Paragraph 38

Extent: E+W+S

(1) No development is to commence until a scheme for the monitoring of the foreshore and sediment levels around the quay has been submitted to and agreed by the MMO, in consultation with the Environment Agency, C.RO and E.ON.
(2) Annual monitoring reports must be submitted to the MMO within 6 weeks of each anniversary of implementation up to 2033.
(3) The approved monitoring scheme must be implemented and complied with at all times.

---
Source: https://www.legislation.gov.uk/uksi/2014/2935/schedule/11/paragraph/38 (the official version)
Page: https://openlegislation.uk/able-marine-energy-park-development-consent-order-2014/schedule-11/paragraph-38
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.