# The Able Marine Energy Park Development Consent Order 2014, Paragraph 5

Extent: E+W+S

Except where the authorised development is carried out in accordance with the drawings listed in paragraph 6, no authorised development may commence until details of the layout, scale and external appearance of the authorised development so far as they do not accord with the drawings listed in paragraph 6 have been submitted to and approved by the relevant planning authorities, and the authorised development must be carried out in accordance with the approved details.

---
Source: https://www.legislation.gov.uk/uksi/2014/2935/schedule/11/paragraph/5 (the official version)
Page: https://openlegislation.uk/able-marine-energy-park-development-consent-order-2014/schedule-11/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.