# The Able Marine Energy Park Development Consent Order 2014, Paragraph 10

Extent: E+W+S

(1) The licence holder is permitted to deposit temporary bog matting upon the foreshore at the Cherry Cob Sands site for the purposes of construction plant movement.
(2) The licence holder must ensure the bog matting is removed as soon as practicable once the activities for which they have been deposited have been completed.

---
Source: https://www.legislation.gov.uk/uksi/2014/2935/schedule/8/paragraph/10 (the official version)
Page: https://openlegislation.uk/able-marine-energy-park-development-consent-order-2014/schedule-8/paragraph-10
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.